Explore this page+
From setting out to concrete
A foundation package starts with the engineer’s current design and finishes with a clearly agreed handover. We coordinate excavation, spoil removal, inspection readiness, reinforcement preparation and concrete logistics around the footprint and access. The approved details determine the foundation type and dimensions.
- Strip and trench-fill foundations
- Ground beams and reinforced slabs
- Blinding, oversites and slab preparation
- Piling mats and associated substructure works
Resolve the interfaces early
Drainage crossings, service sleeves, steps in level, existing foundations and neighbouring structures can all affect the sequence. These details are easier to coordinate before the dig than after concrete is booked. Where the design or ground information is incomplete, we identify the decision needed before work proceeds.
- Latest structural drawing revision
- Ground investigation or trial-pit information
- Drainage and service routes
- Tree and adjoining-structure constraints
Plan the concrete pour
Concrete access, pump position, delivery sequence and inspection availability need to fit the site programme. We review the working area, protection of excavations and the next trade’s requirements so the proposal includes the practical operations around the measured concrete quantity.
What to send for a foundation quote
Start with the site address, structural and architectural drawings, access photos and your target date. Include available survey, drainage and ground information. If you are still at the design stage, tell us what is confirmed so we can distinguish a preliminary review from a fully defined quotation.